Hong Kong Court Clarifies Threshold for Setting Aside Awards

A Hong Kong Court recently adopted a resoundingly pro-arbitration stance in a decision which emphasised the high thresholds of irregularity that would need to be established before an arbitration award can be set aside.

In LY v HW, [2022] HKCFI 2267, the Court dismissed an application to set aside an award based on claims that the Tribunal had failed to deal with the key issues and failed to provide sufficient reasons for its decision in the award. This decision underlines the narrow manner in which grounds for refusal of enforcement are to be construed and fortifies the enforceability of arbitration awards in Hong Kong. Continue reading

MALAYSIAN HIGH COURT UPHOLDS ARBITRATOR DISCRETION IN DECISION MAKING

The Malaysian High Court has set a useful precedent for arbitrator discretion when writing reasons in arbitration awards. In Allianz General Insurance Company Malaysia Berhad v Virginia Surety Company Labuan Branch, Originating Summons No. WA-24NCC(ARB)-13-03/2018, the Court dismissed an application to set aside a majority arbitration award under Section 37 of the Malaysian Arbitration Act 2005 (MAA) for alleged breaches of natural justice predicated on the drafting of the arbitrators’ reasoning.

This case provides an authoritative statement protecting the decision-making latitudes of Malaysian-based tribunals, providing a reminder of Malaysia’s arbitration-friendliness and committed alignment with international best practices in arbitration.

Background

The grounds for setting aside arbitration awards under Malaysian law replicate those of the UNCITRAL Model Law but with slight modification. Under Section 37(2)(b)(ii) MAA, awards can be set aside where there has been “a breach of the rules of natural justice in connection with the making of the award“. A natural justice challenge assesses the arbitration’s compliance with due process requirements. In Allianz, the plaintiff sought to extend the scope of the natural justice ground to cover the manner in which the arbitrators’ reasoning was set out in the majority arbitration award.

The award determined a dispute on the subsistence and interpretation of two reinsurance agreements. The plaintiff was an insurer providing insurance cover for motor vehicles under an extended warranty programme. The defendant provided long-term reinsurance cover for the extended warranty programme, which was recorded in two “treaty” agreements between them.

Both agreements contained express provisions on reinsurance coverage periods, which deemed a mutual intent to terminate the policies at their next anniversary dates. This deemed intent was effected by provisional notices of cancellation (PNOC) being issued automatically 90 days before their next anniversary dates, unless the parties advised otherwise. A dispute arose regarding the actual meaning of the PNOC regime; whether both agreements were renewed; and whether there existed a duty of utmost good faith between the parties. This dispute subsequently went to arbitration seated in Malaysia before a three-member tribunal.

The majority of the tribunal dismissed the claim and issued a majority award in favour of the defendant. A separate dissenting award was issued by the remaining arbitrator. Dissatisfied with the majority award, the plaintiff applied to the Malaysian High Court to set it aside under, amongst others, Section 37(2)(b)(ii) MAA on grounds that the tribunal’s majority had breached natural justice requirements.

The alleged natural justice breach was that the majority award failed adequately to address the issue and submissions on the duty of utmost good faith, which it viewed as a fundamental issue to be determined by the tribunal. To substantiate this alleged failure, the plaintiff emphasised that the tribunal’s majority had only made reference to the utmost good faith principles in four paragraphs of the majority award. The defendant denied that there had been any such alleged infraction by the tribunal.

Malaysian High Court’s decision

The plaintiff’s natural justice challenge against the majority award was dismissed in its entirety. In its decision, the Malaysian High Court emphasised that natural justice did not entitle an arbitral party to receive an arbitrator’s response to all submissions and arguments presented. It was sufficient that the parties were given a right to be heard on these matters.

This further meant that the arbitrators were not bound to explain their disagreement with the plaintiff’s position regarding the existence of an utmost good faith duty beyond the four paragraphs in the majority award. The arbitrators’ choice not to do so could therefore not be an immediate basis to suggest a breach of natural justice and due process.

Preserving arbitrator discretion

The Malaysian court’s decision gives significant assurance to Malaysian-seated tribunals. It highlights the latitude afforded to arbitrators under Malaysian law in determining what issues and arguments are essential in order to write the arbitration award. When identifying what is “essential”, arbitrators are given the discretion to find that a question can be determined without further consideration of certain issues.

Where an arbitrator does address an issue, the High Court in Allianz made it clear that the arbitrator cannot legitimately be expected to “religiously follow the stance or any specific arguments presented by one party or the other” (see also Intraline Resources Sdn Bhd v Exxonmobil Exploration and Production Malaysia Inc [2017] MLJU 1299 at [88]). Arbitrators have discretion to reformulate and refashion the way in which different arguments and concepts have been consolidated, and to make their own value judgements and conclusions between the range of contentions made before it.

Although not raised in Allianz, it is likely that the international practice of allowing issues to be addressed implicitly in an award would have found favour with the Malaysian High Court. Arbitrators generally do not need to address all issues expressly, particularly those with outcomes tied to the conclusion of a specific logically prior issue. In such event, arbitrators can dispense with an assessment of the merits of the arguments and evidence for the former, thus making the decision-making process and arbitration award more efficient (see TMM Division Maritima SA de CV v Pacific Richfield Marine Pte Ltd [2013] 4 SLR 972 at [72]-[74]).

Malaysia’s arbitration-friendliness

Overall, Allianz demonstrates Malaysia’s commitment to upholding arbitral awards. As the Malaysian High Court has emphasised, the court will not treat Section 37 MAA as an appellate provision. Where the provision is invoked, Malaysian courts are required to refrain from sitting in appeal over the arbitrator’s decisions by re-examining and re-assessing the materials brought in the arbitration (see also Antara Steel Mills Sdn Bhd v CIMB Insurance Brokers Sdn Bhd [2015] 5 CLJ 1018).

This approach is particularly reassuring where a set aside application is premised on an alleged breach of public policy, which could be an inherently amorphous assessment. Allianz makes clear that, in such cases, the Malaysian courts adopt a similar approach to that taken by other Model Law jurisdictions (see also Jan De Nul (M) Sdn Bhd & Anor v Vincent Tan Chee Yioun & Anor [2019] 2 MLJ 413 at [41]-[58]; Sigur Ros Sdn Bhd v Master Mulia Sdn Bhd [2018] 3 MLJ 608).

While the ultimate outcomes of recent public policy-based challenges before Malaysian courts have been very consistent, the way in which the Malaysian courts have interpreted the concept of public policy or phrased the test under Malaysian law has been far less consistent. The High Court in Allianz provided helpful guidance in summarising the current Malaysian approach to public policy-based challenges under the MAA:

  • The concept of public policy, and breaches of it, has to be assessed narrowly and restrictively. This accords with the peremptory principle that the court’s curial intervention should be sparingly used, keeping with Section 8 MAA (Article 5 UNICTRAL Model Law).
  • The threshold to be met for a public policy-based challenge is a high one. By its nature, “it should be immediately obvious or at least fairly rapidly apparent that there has been such a breach“.
  • The mere fact that an arbitration award is irrational or unreasonable will not justify its setting aside. When considering a public policy-based challenge, the concept of public policy must be one taken in the “higher sense, where some fundamental principle of law and justice is engaged, some element of illegality, where enforcement of the award involved clear injury to public good or the integrity of the court’s process and powers will thereby be abused“.

Malaysian courts should be slow in accepting arguments that a breach of public policy, including where the rules of natural justice are involved, occurred where this results in an arbitration award being set aside.

Conclusion

The judicial consideration of the Malaysian set aside regime in Allianz is important, as it provides an encouraging restatement of Malaysia’s arbitration-friendly philosophy in public policy-based challenges, particularly those involving elements of natural justice. Tribunals in arbitrations governed by Malaysian law can therefore rest with a degree of assurance when exercising their discretion in the deliberation of issues and their drafting of arbitration awards in making their arbitrations more efficient.

For further information, please contact Peter Godwin, Regional Head of Practice – Dispute Resolution, Asia and Managing Partner, Kuala Lumpur, Lim Tse Wei, Associate, or your usual Herbert Smith Freehills contact.

Peter Godwin
Peter Godwin
Managing Partner
+60 3 2777 5104

Tse Wei Lim
Tse Wei Lim
Associate
+60 3 2777 5135

Disclaimer

Herbert Smith Freehills LLP is licensed to operate as a Qualified Foreign Law Firm in Malaysia. Where advice on Malaysian law is required, we will refer the matter to and work with licensed Malaysian law practices where necessary.

 

MALAYSIAN HIGH COURT CONSIDERS THE LEGALITY OF AN UNDERLYING CONTRACT WHICH WAS THE SUBJECT OF ARBITRATION

In Calibre M&E Sdn Bhd v PT Cooline HVAC Engineering (Originating Summons Nos. WA-24C(ARB)-47-09/2017 and WA-24C(ARB)-49-10/2017), the Malaysian High Court  considered an application to set aside an arbitral award on the basis that the recognition by the tribunal of the allegedly illegal underlying contract was in conflict with the public policy of Malaysia.  Section 37 of Malaysia’s Arbitration Act 2005 (“Act“) (which is modelled after the Article 34 of the UNCITRAL Model Law on International Commercial Arbitration 1985 (as amended in 2006)) allows an award to be set aside on the basis that the award is in conflict with the public policy of Malaysia.

Continue reading

ENGLISH COURT FINDS ONE ERROR OF LAW BUT DECLINES TO OVERTURN AWARD UNDER S69 ARBITRATION ACT 1996

The English High Court (the Court) in Eleni Shipping Limited v Transgrain Shipping B.V. [2019] EWHC 910 (Comm) has reviewed an arbitral award, following an appeal on a point of law brought under s69 Arbitration Act 1996 (s69 AA 1996), and determined that the tribunal made an error of law. While the Court ultimately refused to overturn the award, as it upheld the tribunal’s interpretation of the second point of law in question, this case is nevertheless significant as a rare example of the Court ruling that the tribunal had erred under s69.

Continue reading

Swiss Federal Tribunal refuses to set aside the Deutsche Telekom v India Award

We previously reported here that a Geneva-seated UNCITRAL tribunal (the “Tribunal“) constituted under the India-Germany Bilateral Investment Treaty dated 10 July 1995 (the “India-Germany BIT”) found India in breach of its treaty obligations in relation to its cancellation of a spectrum allocation contract[1] (the “Contract“) in an interim award dated 13 December 2017 (the “Award“).

The Contract was entered into in 2005 between Devas Multimedia Private Limited (“Devas“), an Indian company and Antrix Corporation Limited (“Antrix“), an Indian state-owned satellite company, wherein Devas agreed to pay a fee in return for the lease of the S-band electromagnetic spectrum provided by two orbiting Indian satellites. In the arbitration before the Tribunal, the Claimant, Deutsche Telekom AG (“DT“) (which indirectly held a 20% stake in Devas via a Singaporean subsidiary) alleged a breach of the fair and equitable treatment standard under the India-Germany BIT.

In the Award, the Tribunal dealt with issues of jurisdiction and liability (leaving aside issues of quantum for a later award), and held that it possessed jurisdiction to hear the dispute and that India had indeed violated the standard of fair and equitable treatment under the India-Germany BIT.

India sought to challenge the Award in the Swiss Federal Tribunal (“Federal Tribunal“), being the court of supervision of the arbitration. In a decision last month, the First Civil Law Court of the Federal Tribunal rejected India’s application for the annulment of the Award by a 3:2 majority in a judgment dated 11 December 2018 (available here (in French)).

Continue reading

English High Court refuses to set aside order for enforcement under s103 in long-running dispute regarding ICC award

The English High Court has refused an application under s.103 of the Arbitration Act 1996 (“AA 1996“) to set-aside an order allowing for the enforcement of an ICC award in England. The decision is the culmination of a long-running dispute in which the award debtor has sought to set-aside the award and prevent enforcement in France, the Seychelles and England. The judgement is the latest illustration of the pro-enforcement approach of the English courts with respect to international arbitral awards, particularly where an award debtor has made efforts in multiple jurisdictions to prevent enforcement against it. While the outcome is not surprising, the level of attention given to the grounds raised by the award debtor, even in the face of issue estoppel, demonstrates the importance placed by the English Court on its New York Convention obligations.

Continue reading