Getting paid: A New Bill to streamline Construction Disputes in Thailand

Construction disputes between contractors and employers in Thailand can take years to be resolved in court or arbitration. This can result in construction work being delayed and sometimes abandoned, and contractors facing financial difficulties. In response, Thailand is considering the introduction of a draft bill titled “Act on the Settlement of Disputes regarding Payment in Construction Contracts”.

The bill is inspired by security of payment legislation in Malaysia and Singapore. The common objectives are to: (i) allow faster and less expensive dispute resolution, (ii) create a specialised authority capable of dealing with the complexities of construction contracts, (iii) ensure that contractors are paid according to the contract, all with a view to easing cash-flow and minimising effects of pricing disputes on work disruption.

Features of the Bill

  • Section 8 restricts ‘pay when paid’ clauses, where payments to subcontractors and consultants are dependent on the employer paying the prime/lead contractor.
  • Section 15 is intended to allow contractors to seek immediate recourse for non-payment. After issuing a demand notice to the employer and where payments remain in arrears, the contractor may initiate adjudication proceedings.
  • Sections 9 and 39 codify the ‘pay now argue later’ principle. While parties may litigate a dispute in court or arbitrate the matter in parallel with adjudication proceedings, an adjudication award will be binding unless and until the court or an arbitrator (depending on the choice of dispute resolution mechanism in the parties’ contract) reaches a final and conclusive finding on the matter in dispute.
  • Sections 40 to 42 address enforcement of the Award.  Payments must be made 15 days after the adjudicator’s award is given or as otherwise specified by the adjudicator.  Upon the employer’s failure to make payment, the contractor may seek payment from the employer’s guarantor or enforce the adjudicator’s award against the employers’ assets as if it were an order of court.

This is a welcomed development.  If passed, the Bill will update Thai law to take account of the commercial realities of the industry and adopting tried and tested approach from other jurisdictions to improve contractor cash flow.

The bill is at the public hearings stage and is being refined to ensure that the bill is effective and practical to the construction market in Thailand.  We are monitoring the bill closely and are ready to assist clients navigate developments in the law.

For more information, contact Warathorn Wongsawangsiri, Amornwit Phesprasert, or Dan Waldek.

 

Warathorn Wongsawangsiri
Warathorn Wongsawangsiri
Partner, Bangkok
+66 2 857 3828
Daniel Waldek
Daniel Waldek
Partner, Singapore
+65 6868 8068
Amornwit Phesprasert
Amornwit Phesprasert
Associate, Bangkok
+66 2 857 3814

Construction Law Masters Podcast: Asia Series – John Bishop, Arbitrator, Mediator, Dispute Board Member

We are pleased to share the third episode in our Construction Law Masters in Asia podcast series in which we welcome distinguished guests from the construction industry from across Asia to discuss their unique experiences and views of various aspects of construction law and practice.

In this episode series, Hew Kian Heong (Partner and Joint Global Head of Construction Disputes based in our Shanghai and Beijing offices) interviews John Bishop, one of the world’s pre-eminent construction experts.  John has over 50 years of experience in the legal and construction industries, having handled thousands of international construction, engineering and energy related disputes as counsel, arbitrator, adjudicator, Dispute Board Member, and mediator in many countries around the world.  John is currently practising as a full time independent arbitrator from bases in Beijing, Hong Kong and London.  He joins us to discuss:

  • Significant milestones in the development of construction law in the last 50 years
  • ADR in action on the Channel Tunnel Project
  • The “memorial” approach in international arbitration
  • Use of Dispute Boards in construction projects
  • Mediation of construction disputes between parties from different cultures

This episode and the soundbites can be found on here.

We hope that you enjoy listening to this episode.

Hew Kian Heong
Hew Kian Heong
Partner and Joint Global Head of Construction Disputes
+86 10 6535 5115

Clarification of NSW building limitation periods: NSW Court of Appeal decision

By Michael Lake, Katherine Mackellar and Samuel Hamilton Lindsay.

In November 2020, the New South Wales Court of Appeal published its reasons in Bandelle Pty Ltd v Sydney Capitol Hotels Pty Ltd.1 The Court affirmed that the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act) provides a long-stop limitation period of 10 years for loss arising from defective building works, irrespective of when defects become apparent.

What this means for you

The Court of Appeal’s decision confirms that section 6.20 of EPA Act provides an absolute bar of 10 years from completion for claims arising from defective building works. Each case will turn on its own facts and merits. However, this decision provides the industry with greater clarity around effective limitation defences available to resist claims for latent defects or other actions relating to allegedly defective work.

Background
Facts

On 2 January 2017, a fire broke out on the ground floor of a building on George Street, Sydney. The fire activated the building’s sprinkler system, which caused damage to the property of Sydney Capitol Hotels (Capitol), a tenant of building’s fifth floor. The fire was said to have started due to defective construction of the building’s exhaust duct system. Capitol therefore brought proceedings alleging that the builder of the exhaust duct system (Bandelle) had breached a duty of care owed to it in carrying out those works.

The building had been constructed pursuant to a development consent granted before 1 July 1998. As such, the fire occurred and Capitol’s claim was brought more than 10 years after the completion of construction.

Bandelle argued that the claim was time-barred by virtue of section 6.20 of the EPA Act (set out  below). Capitol, on the other hand, argued that the limitation period in section 6.20 should be construed narrowly to apply to defective works claims between parties to a building contract. On this basis, Capitol argued that section 6.20 was not applicable to its claim because the parties were never in a contractual relationship.

Relevant provisions and previous decisions

Section 6.20(1) of the EPA Act provides:

A civil action for loss or damage arising out of or in connection with defective building work or defective subdivision work cannot be brought more than 10 years after the date of completion of the work.

The predecessor of section 6.20 (section 109ZK) was drafted in similar terms. Earlier appellate case law in relation to section 109ZK had held that the section regulated liability between those carrying out work (and those with responsibility for its sufficiency) and the ultimate beneficiaries of the work, rather than changing the scope of liability more generally. In particular, in Dinov v Allianz Australia Insurance,2 the NSW Court of Appeal held that section 109ZK did not apply to an action brought by an insurer to enforce an indemnity under a home building insurance policy against the directors of an insolvent builder. The Court of Appeal in that case held that such an action was not one ‘arising out of or concerning defective building work’.

At first instance in the Capitol decision, Hammerschlag J indicated that he favoured a view that Capitol’s claim was covered by section 6.20.3 However, his Honour considered that he was bound to apply the previous interpretation given to section 109ZK in cases including Dinov, with the result that section 6.20 of the EPA Act did not apply to claims that were only ‘accidentally, incidentally or indirectly’ affected by defective construction.

Capitol was a tenant of the building and had no contractual relationship with the builder. Further, the losses were considered incidental to the defective building works: the fire had caused Capitol’s losses, rather than the defective construction of the building’s exhaust duct system. Accordingly, Hammerschlag J decided that the limitation period under section 6.20 of the EPA Act did not apply to Capitol’s claim.

The decision appeared to provide an avenue for owners and occupiers to circumvent the 10-year limitation period, and seek to pursue actions (at least in some circumstances) against builders in relation to building work completed more than 10 years before.

The Court of Appeal decision

The decision of Hammerschlag J was overturned on appeal. The Court of Appeal held that section 6.20 of the EPA Act applies to all claims for loss caused by defective building work, and is not limited only to claims for pure economic loss, related to latent defects, or brought by owners as opposed to tenants. As such, section 6.20 extended to Capitol’s claim for loss arising due to the fire caused by the defective exhaust duct system.

The Court of Appeal further confirmed that section 6.20 provides a 10 year long-stop limitation period which applies from when the works were completed, irrespective of when the defect becomes apparent.

Accordingly, a majority of the Court held that Capitol’s claim was barred by section 6.20, having been brought significantly later than 10 years after completion of the works.

This conclusion followed a detailed analysis of the legislative of history of section 6.20, in which the Court of Appeal considered a number of issues. These included:

  • application of section 6.20 to pre-1998 work. Transitional regulations brought into existence when section 109ZK was initially introduced provided that the limitation period only applied to works completed under development consents granted after July 1998. The majority held that, since that transitional regulation had been repealed with effect from 2012 and no such limitation applied to section 6.20, the current limitation period applies to all works irrespective of when development consent may have been given. Emmett AJA, in dissent, held that section 6.20 only applies to building works conducted pursuant to development consents granted after July 1998.
  • the period between s109ZK repeal and s 6.20 commencement. On a literal construction, section 109ZK was repealed on 1 March 2018, however due to the intricacies of the commencement and transitional provisions, section 6.20 did not commence until 1 December 2019. The Court unanimously found that section 6.20 applied from 1 March 2018 and that there was no gap where neither provision applied. The Court justified the departure from a literal transition by reference to the purpose of the provisions and their importance to public safety.
Interaction with Design and Building Practitioners Act 2020 (NSW)

The decision is significant in light of the Design and Building Practitioners Act 2020 (NSW) (DBP Act), which came into force on 11 June 2020. The DBP Act imposes a statutory duty of care on any person who carries out ‘construction work’ to exercise reasonable care to avoid economic loss caused by defects. The duty extends to a range of practitioners including those:

  • carrying out building work (including residential building);
  • preparing designs for building work;
  • manufacturing or supplying building products used for building work; and
  • supervising, coordinating or project managing the works listed above.

An action for breach of the new statutory duty, like the negligence action brought by Capitol, accrues when damage or loss is suffered. As such, the action may not accrue until a number of years after completion of the work. Further, the statutory duty has retrospective effect, extending to construction work completed before the commencement of the legislation (provided that any losses from a breach of duty arise within the 10 years immediately before 11 June 2020, or after that date).

However, the statutory duty is subject to the usual limitation periods under the Limitation Act 1969 (NSW), the Home Building Act 1989 (NSW) and the EPA Act, so the potential period of liability is not unlimited. The Court of Appeal’s decision provides welcome certainty as to the broad scope of application of s 6.20 of the EPA Act to actions brought in relation to the statutory duty.

Endnotes
  1. Sydney Capitol Hotels Pty Ltd v Bandelle Pty Ltd [2020] NSWCA 303.
  2. Dinov v Allianz Australia Insurance Limited (2017) 96 NSWLR 98 (Dinov), [107]. See also Australian Rail Track Corporation Ltd v Leighton Contractors Pty Ltd [2003] VSC 189.
  3. Sydney Capitol Hotels Pty Ltd v Bandelle Pty Ltd [2019] NSWSC 1825, [23].

 

Geoffrey Hansen
Geoffrey Hansen
Partner
+61 3 9288 1892
Clare Smethurst
Clare Smethurst
Partner
+61 7 3258 6623
Dan Dragovic
Dan Dragovic
Partner
+61 8 9211 7600
Ante Golem
Ante Golem
Partner
+61 8 9211 7542
Michael Lake
Michael Lake
Senior Associate
+61 2 9322 4318
Katherine Mackellar
Katherine Mackellar
Solicitor
+61 2 9225 5519

English court restrains expert from acting in arbitration due to breach of fiduciary duty of loyalty – A Company v X, Y and Z [2020] EWHC 809 (TCC).

English court restrains expert from acting in arbitration due to breach of fiduciary duty of loyalty – A Company v X, Y and Z [2020] EWHC 809 (TCC).

 

Summary

Earlier this month, the English High Court extended an interim injunction restraining a global expert consultancy firm from acting as independent experts in separate, although related, arbitration proceedings against the claimant.[i]

In granting the claimant’s application to extend the interim injunction, the court held that:

  1. Not only did the expert firm’s subsidiary engaged by the claimant owe a fiduciary duty of loyalty to its client, that fiduciary duty extended to the defendant group (i.e. the second and third defendants) as a whole.
  2. The defendant group’s fiduciary duty of loyalty was not satisfied by putting in place information barriers. Measures such as this seek to preserve confidentiality and privilege. A fiduciary with a duty of loyalty must not place himself in a position where his duty and his interest may conflict.
  3. The defendant group breached its fiduciary duty by accepting instructions to provide expert services in connection with the second arbitration without first obtaining the claimant’s consent. The court’s finding that the two arbitrations are concerned with the same delays, and that there is a sufficiently significant overlap in the issues, underpinned its conclusion that the defendants breached their duty to the claimant.

Continue reading

COVID-2019: Insurance and Construction Projects Podcast

In our latest podcast, James Doe (Partner, UK Head of Construction & Infrastructure Disputes), Emma Schaafsma (Partner, Construction & Infrastructure Disputes) & Sarah McNally (Partner, Insurance Disputes) look at how construction contracts are currently being affected by COVID-2019 and the extent to which insurance cover might protect against losses.

 

This episode can be found on Soundcloud, Spotify and iTunes.

 

James Doe
James Doe
Partner and UK Head of Construction & Infrastructure Disputes, London
+44 20 7466 2583
Emma Schaafsma
Emma Schaafsma
Partner, Dispute Resolution
+44 20 7466 2597
Sarah McNally
Sarah McNally
Partner, Insurance Disputes
+44 20 7466 2872

Who’s Who Legal highlight Partner David Nitek in their latest thought leaders guide

London-based Construction & Infrastructure Disputes Partner David Nitek has been profiled as a thought leader in Who’s Who Legal’s latest Thought Leaders: Construction guide. The guide brings together the world’s foremost practitioners in the sector, giving access to their insight and expertise.

Described as an ‘excellent disputes lawyer’ with a ‘keen mind for complicated technical issues’ he discusses his career, what he views as the main legal challenges in construction and how he approaches dispute resolution in the interview here.

 

 

David Nitek
David Nitek
Partner, London
+44 20 7466 2453