Extensions of time – the starting point

On 10 February 2017, the Court of Appeal released its decision in the case of Carillion Construction Limited v Emcor Engineering Services Limited and Anor [2017] EWCA Civ 65.

This case concerns the situation in which a Relevant Event (a delay event) occurs after the contractual completion date. The Court of Appeal confirmed the Technology and Construction Court’s (“TCC’s”) earlier decision that clause 11.3 of the subcontract in question required an extension of time to be contiguous; meaning that the period of extension should run from the contractual due date for completion and not the date on which the impact of the delay event was felt.