Qld: Extension of termination date for the Queensland Rail 2008 undertaking

On 9 April 2015, Queensland Rail (QR) requested an extension to the termination date of the QR Network Access Undertaking (2008) June 2010 (2008 Access Undertaking) from the Queensland Competition Authority (QCA). QR has requested that the 2008 Access Undertaking be extended until the earlier of: 30 June 2016, or the date on which the … Read more

Extension of time for the Queensland Rail 2008 undertaking

On 5 November 2014 Queensland Rail requested an extension to the termination date of QR Network’s (2008) June 2010 Access Undertaking (2008 Access Undertaking), which is currently set to expire on 31 December 2014. QR requested this extension following submission of Queensland Rail’s Draft Access Undertaking 1 (AU1) which is proposed to replace the 2008 … Read more